Louis Armstrong New Orleans International Airport



Capital improvements
Interior Terminal Improvements: Phase 3 (Terminal and Baggage Claim)

 
NOAB Project 1065

 
Overview

This project provides for the modernization of the interior of the Main Terminal building. On Level 2, the offices on the roadway side of the main corridor will be demolished up to the curtain wall and will be reconfigured into a circulation area with new Terrazzo flooring. The ticket counters will be refurbished and relocated to allow for the placement of EDS machines behind them. Level 1 modernization efforts consist of upgrades to the flooring and baggage claim finishes. This project was bid with the Exterior Terminal Improvements Phase 2 project (NOAB Project #1067) and has been coordinated to mitigate passenger and tenant impacts.
 
Project Personnel

Construction Schedule





Project Manager

Harvey Goldstein, ART

  Notice to Proceed

8-16-10

Architect/Engineer

Murray Architects

  Project Duration (Days)

360

Contractor PM

Steven Sentiles

  Completion Date

8-10-11

Contractor

Gibbs Construction

  Delay/Extension (Days)

222

      Revised Completion Date

4/2013


Project Budget



Costs     Percentage
Construction

$7,262,155

     
Change Orders

2,957,885

   40.7%  
Design

$267,181

   3.7%  
Other

$101,500


1.4%
PM/CM

$590,419


8.1%
Total

$11,179,140

   
 
Project Status
  • Construction closeout 4/2013 with project closeout to be completed 5/2013