Louis Armstrong New Orleans International Airport



Capital improvements
North Perimeter Road Improvements

        NOAB Project 1083


Overview
This project provides for the rehabilitation and realignment of the existing North Perimeter Roadway into a new, wider road that is easier to navigate. Also included in this project is the re-contouring of nearby drainage ways. The project was originally combined with the Runway 6-24 Conversion Project (NOAB Project #1086) , but was split apart due to funding issues.
 
Project Personnel

Construction Schedule





Project Manager

Jay Scalise, ART


Notice to Proceed

01-18-11

Architect/Engineer

Lambert Engineers, LLC


Project Duration (Days)

270

Contractor PM

John Rodriguez


Completion Date

10-18-11

Contractor

Gibbs & Register Inc.


Delay/Extension (Days)

55




Revised Completion Date

11-09-11

Project Budget








Costs

Percentages
Construction

$2,964,313




Change Orders

$147,511


4.9%
Design

$371,709


15.5%
Other

$220,000


7.4%
PM/CM

$392,051


13.2%
Total

$4,095,584




 
Project Status
  • The rehabilitation and realignment of the existing North Perimeter Road to a new wider roadway that is easier to navigate.
  • Construction, Change Order, Design, and Other costs are costs approved by the Board.
  • The PM/CM cost is actual spending as of November 2011.
  • Other costs include Resident Inspection and Materials Testing services.
  •