Capital improvements
Capital Improvements > Projects in Closeout

<< Return

Projects in Closeout
Name 
Aircraft Loading Bridges
This project provided for the replacement of 17 aircraft loading bridges. It was divided into two phases: Base Bid, which replaced 10 bridges and Bid Option #1, which replaced 7 bridges.
 
 
 
 
 
 

Consolidated Rent-A-Car (CONRAC) Garage
This project provides for the construction of a customer service building, a ready-return parking garage, new utility building and associated service areas for the rental car companies to maintain their vehicles. The facility will also include concessions and will be connected to the Terminal via covered walkways.
 
 
 

Exterior Terminal Improvements: Phase 2
This project provides for the modernization of the exterior features of the Terminal building. On the upper level, the curtain wall façade will be replaced with windows and new entrances. Expansion joints along the Terminal façade will be replaced. The inner and outer roadway curbs will be expanded by 3 ft on both levels and roadway lane widths will be narrowed accordingly. This project was bid with the Interior Terminal Improvements Phase 3 project and has been coordinated to mitigate passenger and tenant impacts.

Interior Terminal Improvements Phase 1 (Restrooms)
This project provides for the complete rehabilitation of 12 restrooms along with minor renovations to an additional 9 restrooms throughout the terminal and all concourses. Work has been phased with other planned/ current interior construction work in the Terminal to minimize impacts to passengers. (This project was originally bid in 2009 but was rebid in 2010).
 
 
 
 
 

Interior Terminal Improvements: Phase 3 (Terminal and Baggage Claim) This project provides for the modernization of the interior of the Main Terminal building. On Level 2, the offices on the roadway side of the main corridor will be demolished up to the curtain wall and will be reconfigured into a circulation area with new Terrazzo flooring. The ticket counters will be refurbished and relocated to allow for the placement of EDS machines behind them. Level 1 modernization efforts consist of upgrades to the flooring and baggage claim finishes. This project was bid with the Exterior Terminal Improvements Phase 2 project and has been coordinated to mitigate passenger and tenant impacts.
New Airfield Rescue and Fire Fighting (ARFF) Facility This project provides a modern ARFF Station just to the west of the existing facility which is both antiquated and located on a constrained site that doesn’t allow for expansion. The project also included the demolition of the DHL hangar and apron.
 
 
 
   
 

Phase 4 (A) Improvements This project includes the reconfiguration of the security checkpoint screening lanes at Concourse D to increase the ingress and egress capacity at the checkpoint. The renovation work will include carpet replacement, painting, speaker replacement, installation of additional lighting, new laptop counters, and reupholstering of all concourse seating. Additional items under this project include replacement of all signage throughout the airport, rehabilitation of the Concourse C tug tunnel, and cleaning of canopies in between the parking garage and terminal.
Phase 4 Interior Terminal Improvements
This project includes a number of aesthetic upgrades including improvements to walls, ceilings, additional lighting, column covers, speakers, carpet replacement, FFE (fixtures, furnishings, and equipment), and replacement of escalators and trash receptacles.




Runway 10/28 Approach Light Relocation (Levee Improvements)
The United States Army Corps of Engineers (USACE) is constructing a series of levee sections on the west end of the airfield. The work has been divided into three separate projects: (1) re-align the West Return Flood Wall, (2) construct the Levee around the "10" end of Runway 10/28  and (3) raise the Canadian National Railroad Gate.  The Airport has been charged with doing the electrical associated with constructing the levee at the 10 end of Runway 10-28. The Corp will perform all other work.
 

Utility Building$9.92M construction completed 8/2013, project closeout scheduled for 8/2013.



 