Capital improvements
Capital Improvements > Projects Completed > Security Perimeter Fence Replacement

<< Return

Security Perimeter Fence Replacement

        NOAB Project 1100


Overview

This project consists of the complete replacement of the perimeter security fence including all gates, barbed wire, razor wire, and automatic gates. The new fence will be constructed 8 feet high with 2 additional feet of fence fabric buried in the ground for increased animal control. This project also includes the demolishing of the existing fence.
 
Project Personnel

Construction Schedule





Project Manager

Kevin Spruell, NOAB


Notice to Proceed

08-16-12

Architect/Engineer

TMG Consulting


Project Duration (Days)

150

Contractor PM

Josh Kalena


Completion Date

01-12-13

Contractor

U.S. Fence & Gate, Inc.


Delay/Extension (Days)

23





Revised Completion Date

5/2013
Project Budget








Costs

Percentage
Construction

$1,946,571




Change Orders

$0




Design

$80,000


3.8%
Other

$100,000


4.7%
PM/CM

In-house




Total

$2,126,571




 
Project Status
    • Security Perimeter Fence Replacement: construction is 50% complete at this time.
    • 100% expected 5/2013.
    • Contract time has been extended 23 due to inclement weather.
     

 

© Copyright 2014, Louis Armstrong New Orleans International Airport. All rights reserved.

Site designed by Bizzuka New Orleans Web Design