Capital improvements
Capital Improvements > Projects Completed > North Perimeter Road Improvements

<< Return

North Perimeter Road Improvements

        NOAB Project 1083


Overview
This project provides for the rehabilitation and realignment of the existing North Perimeter Roadway into a new, wider road that is easier to navigate. Also included in this project is the re-contouring of nearby drainage ways. The project was originally combined with the Runway 6-24 Conversion Project (NOAB Project #1086) , but was split apart due to funding issues.
 
Project Personnel

Construction Schedule





Project Manager

Jay Scalise, ART


Notice to Proceed

01-18-11

Architect/Engineer

Lambert Engineers, LLC


Project Duration (Days)

270

Contractor PM

John Rodriguez


Completion Date

10-18-11

Contractor

Gibbs & Register Inc.


Delay/Extension (Days)

55




Revised Completion Date

11-09-11

Project Budget








Costs

Percentages
Construction

$2,964,313




Change Orders

$147,511


4.9%
Design

$371,709


15.5%
Other

$220,000


7.4%
PM/CM

$392,051


13.2%
Total

$4,095,584




 
Project Status
  • The rehabilitation and realignment of the existing North Perimeter Road to a new wider roadway that is easier to navigate.
  • Construction, Change Order, Design, and Other costs are costs approved by the Board.
  • The PM/CM cost is actual spending as of November 2011.
  • Other costs include Resident Inspection and Materials Testing services.
  •  

 

© Copyright 2014, Louis Armstrong New Orleans International Airport. All rights reserved.