Expansion of Concourse D

        NOAB Project 0974

Photo by Michael Palumbo

Overview
This project provides an additional six (air carrier) gates to the current seven gates on Concourse D. Also included are new food and beverage concessions, retailers, restrooms and modifications to the security checkpoint that will allow for the increased capacity.
 
Project Personnel

Construction Schedule





Project Manager

Tim Murray, ART


Notice to Proceed

3-29-10

Architect/Engineer

Sizeler/Thompson/Brown


Project Duration (Days)

545

Contractor PM

John Manion


Completion Date

9-24-11

Contractor

The McDonnel Group


Delay/Extension (Days)

13




Revised Completion Date

10-08-11

Project Budget








Costs

Percentage
Construction

$16,849,000




Change Orders

$386,661


2.3%
Design

$4,189,987


24.9%
Other

$614,000


3.6%
PM/CM

$1,176,394


6.9%
Total

$23,216,042




 
Project Status
  • The Expansion of Concourse D will add approximately 56,000 square feet of building space consisting of new restrooms, future concession space, and hold rooms all to support the addition of six new Airline Jet Bridge Gates.
  • After Katrina, the project was completely redesigned to meet new airport and airline requirements.
  • *Original dates not shown because it was a pre-Katrina schedule.
  • Construction, Change Order, Design, and Other costs are costs approved by the Board.
  • The PM/CM cost is actual spending as of December 2011.
  • Other costs include Resident Inspection, Demolition, and Materials Testing services.



 