Airfield Rescue and Fire Fighting (ARFF) Facility

        NOAB Project 0978

Overview

This project provides a modern ARFF Station just to the west of the existing facility which is both antiquated and located on a constrained site that didn't allow for expansion. The project also included the demolition of the DHL hangar and apron.
Project Personnel

Construction Schedule





Project Manager

Jay Scalise, ART


Notice to Proceed

10-23-09

Architect/Engineer

Hegedus-ECM Architects


Project Duration (Days)

365

Contractor PM

Steven Mendoza


Completion Date

10-22-10

Contractor

Satterfiled & Pontikes Construction , LLC


Delay/Extension (Days)

325




Revised Completion Date
9-12-11
Project Budget




Costs

Percentage
Construction

$9,913,000




Change Order

$396,000


4.0%
Design

$1,084,177


10.9%
Other

$376,367


3.8%
PM/CM

$870,142


8.8%
Total

$12,639,686




Project Status
  • Construction completed 6/2013, project closeout scheduled for 7/2013.

 


 